Progress of the projects carried out by the council in following years

Current status of the projects in year 2023

Click on below link to see the details

Current status of the projects in year 2022

Click on below link to see the details

Renovation of Basavakkulam car park with gravel – 2023

Renovation of Prabhavi Preschool – 2023

Budget (Rs:): 1,980,407.00
Contracted amount(Rs:): 1,800,370.00
Society/ Contractor: Nuwara weva Community Board
Contract period: 2023.04.26-2023.07.26
End Date: 2023.07.05
Equity Payout Value: 
Final payment value: 1,919,865.51
Amount currently paid: Financial progress:
Physical progress: 100%
Value of bills in hand: 1,919,865.51
Other Matters: Final payment is due

Laying the foundation stone for the construction of Sahana Shakti Welfare Society Hall – 2023

Modernization of Sunatha Rest House – 2022

Renovation of Mahanama Uyana Eighth Lane – 2022

Saliya Mawatha Eighth Lane Reconstruction – 2022

Development of sewage and sewage transport system – 2022



Construction of public market staircase – 2022

Reconstruction of Municipal Roads